Investment Analysis and Net Present Value (NPV): A Detailed Example
In this blog post, we'll dive deep into the financial analysis of an investment project, using the Net Present Value (NPV) method. NPV helps us assess the profitability of an investment by considering the time value of money. Here's a detailed breakdown of a real estate development project, including costs, cash flows, and the NPV calculation over a period of 10 years.
Project Overview
A business is embarking on a new project to develop a head office building, which will take place over several years. Here's the basic structure of the project:
- Year 0 (Initial Investment): Site acquisition costs £4.5 million.
- Year 1 to 3: Costs related to assessment, planning, foundation, and building structure.
- Year 4: Fitting out the building, handover, and other related costs.
- Year 5: Sale of the old site generating £2.2 million.
After the building is completed in Year 5, the company expects an increase in profitability from the new site, contributing £2.1 million per year from Year 5 to Year 10.
Key Assumptions
- Inflation: 2% annually.
- Investment Rate: 8% per year.
- Discount Rate (DF): 6%, which is derived from the investment rate minus the inflation rate.
- Cash Flow: In years prior to Year 5, there are significant costs, but starting in Year 5, there is an expected profitability increase of £2.1 million annually (adjusted for inflation).
We will now calculate the NPV over the 10 years, using these assumptions to assess the project's financial viability.
Year-by-Year Breakdown
The following table summarizes the project’s cash flow, discount factors, and present value (PV) for each year.
| Year | Cash Flow (Vi, £k) | Cost Benefit (£k) | Sum of Vi (£k) | Cumulative Vi (£k) | Discount Factor (DF) | Present Value (PV, £k) | Cumulative PV (£k) |
|---|---|---|---|---|---|---|---|
| 0 | -4500 | 0 | -4500 | -4500 | 1.000 | -4500 | -4500 |
| 1 | -400 | 0 | -400 | -4900 | 0.943 | -377.2 | -4877.2 |
| 2 | -800 | 0 | -800 | -5700 | 0.890 | -712 | -5589.2 |
| 3 | -2700 | 0 | -2700 | -8400 | 0.840 | -2268 | -7857.2 |
| 4 | -2500 | 2100 | -400 | -8174 | 0.792 | -316.8 | -8174 |
| 5 | 2200 (sale of site) | 2100 | 4300 | -4500 | 0.747 | 3213 | -4960.2 |
| 6 | 0 | 2100 | 2100 | -2400 | 0.705 | 1485 | -3475.2 |
| 7 | 0 | 2100 | 2100 | -300 | 0.665 | 1397 | -2078.2 |
| 8 | 0 | 2100 | 2100 | 1800 | 0.627 | 1317 | -761.2 |
| 9 | 0 | 2100 | 2100 | 3900 | 0.592 | 1243.2 | 482.0 |
| 10 | 0 | 2100 | 2100 | 6000 | 0.558 | 1171.8 | 1653.8 |
How the NPV Is Calculated
Year 0: The investment begins with an initial cost of £4.5 million. The discount factor (DF) for Year 0 is 1, and the present value (PV) is simply the cash flow of -£4.5 million.
Years 1-3: During these years, the company faces costs for assessment, planning, and foundation work. The cash flow (Vi) is negative, and the PV is calculated by multiplying the cash flow with the respective discount factor (DF) for each year.
Year 4: In this year, the company incurs an additional cost but also gains a £2.1 million cost benefit. This contribution will be added to the overall cumulative cash flow.
Year 5 and Beyond: Starting from Year 5, the company starts seeing the benefits of the new building, which contributes £2.1 million per year, adjusted for inflation. These cash inflows continue for the next five years (Year 5 to Year 10).
Key Observations
The discount factor (DF) decreases as the number of years increases. This reflects the time value of money: cash flows in the future are worth less than immediate cash flows.
By Year 10, the project has accumulated a positive cumulative PV of £1653.8k, meaning the project will eventually become profitable.